The control system of hydroelectric unit №6 for "Zagorskaya" pumped-storage hydro power plant was put into operation

05.07.2010

SPC "Rakurs" has completed the works on modernization of the control system of hydroelectric unit in full and in the terms fixed by the schedule program. After carrying out of acceptance tests the hydroelectric unit was put into operation.

In 2010 the control system of the hydroelectric unit №6 for "Zagorskaya" pumped-storage hydro power plant is planned to adopt. The equipment was shipped by SPC "Rakurs" in the end of June.