TRAINING STAND OF AUTOMATED CONTROL SYSTEM SOFTWARE AND HARDWARE COMPLEX
  • Карта проектов. Выполнено по всему миру 1000 проектов

  

Reference list

TRAINING STAND OF AUTOMATED CONTROL SYSTEM SOFTWARE AND HARDWARE COMPLEX

31.08.2012

On August 22 SPC Rakurs shipped the training stand of automated control system software and hardware complex within the frames of Boguchanskaya HPP automation project.

The training stand has been designed for the following tasks of maintenance personnel training:

· Controllers and intelligent devices maintenance;

· Networking equipment maintenance;

· Computer equipment maintenance;

· Software and hardware complex equipment faults search and clearance;

· Corrective actions in controllers and visualization system software.

The training stand in package with simulator of hydro unit automated control software and hardware complex has been designed for operating personnel training in hydro unit modes control.

The product is a combination of equipment assembly 19” vertical frames based on Rittal Data Rack 7396.000 distribution frame and panels based on Rittal TopPult TP system. The stand has been designed on a base of Omron controllers of CJ series. Information exchange between the sections is realized by Ethernet, Profibus, Modbus networks. Duplicated controller CJ2H CPU65-EIP, remote controller modules SmartSlice (Omron), NS (Omron) and EXTER (Beijer Electronics) terminals are located on the stand.

The training stand computer equipment includes the following: server, work station, engineering station (notebook computer) and embedded computer.

Rakurs specialists have been currently performing works on equipment adjustment at the site.

Within the frames of package supply of automated control system software and hardware complex for Boguchanskaya HPP SPC Rakurs has shipped the following equipment:

· Automated control system software and hardware complexes for nine hydro units containing:

· PTC of Francis turbine control;

· PTC for Francis turbine oil-pressure installation and auxiliary equipment control;

· PTC of hydro unit automated control;

· PTC of hydro unit measurement and alarm system;

· PTC of block transformers diagnostics system;

· PTC of hydro power plant house transformers diagnostics system – 4 pcs.;

· PTC of hydro power plant autotransformers diagnostics system – 2 pcs.