12.12.2014
In December the permanently installed system of monitoring, diagnostics and vibration was successfully placed in commission for Bratsk Hydroelectric Power Station.
It has been realizing as part of invest programme of IrkutskEnergo in 2014. Supply and place in commission of this system is already third project for Bratsk Hydroelectric Power Station during 2 years. First supply of the system was realized in December 2013 for hydroelectric generating set 16, the second one was realized in May 2014 for hydroelectric generating set 17.