16.08.2012
On August 7 a training seminar based on Siemens new technical solutions was held for Rakurs Group’s engineers. It was conducted by the company’s representatives in the sphere of industrial automation concerning Siemens up-to-dated engineering products.
10.08.2012
Rakurs has shipped electric part of regulating and protecting system for ПТ-140/165-130/15-3 steam turbine of Volzhskaya TPP-2.
Software and hardware complex (PTC) of electric part of regulating and protecting system has been designed on a base of software and hardware measurement complex Apogey, ТУ4252-003-27462912-04. The scope of work includes designing, packaging, manufacturing, delivery and adjustment.
02.08.2012
SPC “Rakurs” and “Rakurs-engineering” have obtained Omron Electronics certificates confirming the status of Competence centre in Russia in energy sector. Being traditional for SPC “Rakurs” obtaining of such a certificate is the first time for Rakurs-engineering, the Group innovation centre and Neudorf SEZ resident. The second certificate issued to Rakurs-engineering confirms the status of Omron Electronics engineering partner.
16.07.2012
Rakurs has shipped electric part of regulating and protecting system of T-100/130 turbine for Novosibirskaya TPP-4.
Software and hardware complex of electric part of regulating and protecting system for steam turbine has been designed on the base of software and hardware measuring complex “Apogey”, ТУ4252-003-27462912-04. The scope of works under the contract includes designing, packaging, manufacturing, supply and adjustment.
03.07.2012
Rakurs equipment for Boguchanskaya HPP hydro units No. 7, 8 and 9 has been successfully tested and completed for shipment. The supply includes equipment of software and hardware complexes of hydro units automated control, hydro unit control cabinets as well as software and hardware complex of transformer equipment diagnostics and monitoring system.
25.06.2012
Rukurs has delivered “Automated control system for hydro unit No.1” and “Software and hardware complex of upper level” to Shulbinskaya HPP in spring 2012. The equipment has been assembling by the contractor at the present moment. Adjustment of the equipment is planned from September to November 2012.
20.06.2012
SPC Rakurs has manufactured and shipped transformer facilities monitoring, control and diagnostics system (ASMUT) for Yugo-Zapadnaya TPP OJSC. It has been designed as integrated functionally completed system with transformer facilities including technical, algorithmic, informational provisions and software. ASMUT has passed measuring channels calibration procedure before being shipped.
18.06.2012
Pursuant to the contract of relay protection and automatic equipment microprocessor devices 500kV Rakurs Group has shipped 26 cabinets for Zagorskaya HPSPP-2 in spring 2012. This supply being a part of Zagorskaya HPSPP-2 automation complex project realized by SPC Rakurs includes the following:
13.06.2012
Rakurs Group specialists have shipped electric part of regulating and protecting system for Т-60/65-130-2М turbine of Barnaulskaya TPP-2.
The scope of works under the contract includes designing, completing, manufacturing, supply as well as adjustment.
09.06.2012
SPC Rakurs’ electric drive department has shipped six СЧРП-4А0200-L variable-frequency electric drive complete cabinets for control of exhausts asynchronous electric